Under a final rule for hexavalent chromium, employee exposures must
be under 5 micrograms per cubic meter of air, a higher limit than the
1 microgram per cubic meter the Occupational Safety and Health
Administration first proposed, according to a final rule published in
the Feb. 28 Federal Register (71 Fed. Reg. 10,100).
The new permissible exposure limit still leaves a significant
health risk, OSHA said, but the new PEL is the lowest level that is
technologically and economically feasible for all industry
sectors.
When it began the rulemaking, OSHA said, the agency believed a PEL
of 1microgram per cubic meter was feasible, but the rulemaking process
revealed otherwise. The "vast majority of commenters," OSHA
said, did not believe the proposed PEL was appropriate.
Under OSHA's previous limit, which was the equivalent of
52 micrograms per cubic meter of CrVI per eight-hour time-weighted average,
the agency estimated that there were between 101 and 351 excess lung
cancer deaths per 1,000 workers, assuming a 45-year workplace
exposure.
Under the PEL in the final rule, excess deaths are estimated at
between 10 and 45 per 1,000 workers, OSHA said. A PEL of
1 microgram per cubic meter would have reduced the figure to between 2.1 and
9.1 deaths.
In a Feb. 27 conference call, Acting OSHA Administrator Jonathan
Snare said that the final rule will result in approximately 40 to 145
avoided cancers per year.
Selected
OSHA Risk Estimates (Excess Cancers per 1000
Workers)
|
Standard |
Risk at prior PEL |
Risk at new PEL |
Federal Register date |
|
Ethylene Oxide |
63-109 per 1000 |
1.2-2.3 per 1000 |
June 22, 1984 |
|
Asbestos |
64 per 1000 |
6.7 per 1000 |
June 20, 1986 |
|
Benzene |
95 per 1000 |
10 per 1000 |
Sept. 11, 1987 |
|
Formaldehyde |
0.43-18.9 per 1000* |
.0056-2.64 per 1000* |
Dec. 4, 1987 |
|
Methylenedianiline |
6-30 per 1000** |
0.8 per 1000** |
Aug. 10, 1992 |
|
Cadmium |
58-157 per 1000 |
3-15 per 1000 |
Sept. 14, 1992 |
|
1,3 Butadiene |
11.2-59.4 per 1000 |
1.3-8.1 per 1000 |
Nov. 4, 1996 |
|
Methylene Chloride |
126 per 1000 |
3.6 per 1000 |
January 10, 1997 |
|
Chromium VI |
101-351 per 1000 |
10-45 per 1000 |
2006 |
* range is based on maximum likelihood estimate (0.43, .0056) and
upper 95% confidence limit (18.9, 2.64) ** no prior standard;
reported risk is based on estimated exposures at the time of the
rulemaking Source: Occupational Safety and Health
Administration |
"However," the preamble to the final rule says,
"even at the new PEL, the risk posed to workers with a lifetime
of regular exposure is still clearly significant."
The risk that remains in the final CrVI rule is higher than that in
many of OSHA's other health standards, the agency noted.
"We understand and acknowledge" that there is a
significant risk at the final limit, Snare said, and that is why the
rule contains ancillary provisions to address the remaining risk.
The hexavalent chromium rule is required under a U.S. Court of
Appeals for the Third Circuit decision on April 2, 2003, that ordered
OSHA to expedite rulemaking on hexavalent chromium and issue a final
rule no later than Jan. 18, 2006 (33 OSHR 349, 4/10/03)--a deadline
that was extended to Feb. 28 (36 OSHR 47, 1/19/06).
Public Citizen Health Research Group, which brought the lawsuit,
sought a PEL of 0.25 microgram per cubic meter.
The agency is publishing separate rules for general industry,
construction, and shipyards, but the major provisions are similar in
each rule.
Welding, Other Industries See Infeasible Limit.
Despite the remaining significant risk under the final PEL, OSHA
said, technological and economical feasibility issues prevented the
agency from setting a lower limit.
There are approximately 558,000 workers exposed to hexavalent
chromium, OSHA said. Of those, 352,000 are exposed at levels above
0.25 microgram per cubic meter and 68,000 are exposed at levels above
5 micrograms per cubic meter.
The definition of technological feasibility, OSHA said,
"recognizes that for a standard based on a hierarchy of controls,
a particular PEL is not technologically feasible simply because it can
be achieved through the widespread use of respirators."
The proposed PEL of 1microgram per cubic meter, OSHA added, is not
feasible because it cannot be achieved through engineering and work
practice controls for all industries--particularly for welding, which
represents the largest portion of workers exposed to hexavalent
chromium.
The lower PEL is also infeasible for aerospace painting, the agency
said, and insufficient evidence exists to establish technological
feasibility for chromate pigment producers, chromium catalyst
producers, chromium dye producers, and some hard chrome
electroplaters.
In a special section for the painting of aircraft or large aircraft
parts, the final rule only requires employers to use engineering and
work practice controls to reduce exposures to or below
25 micrograms per cubic meter. The employer must then use respiratory
protection to achieve the PEL.
In total, OSHA said, at the final PEL of 5 micrograms per cubic meter,
only 3.5 percent of exposed employees will be required to use
respirators.
In the Feb. 27 conference call, Amanda Edens, the director of
OSHA's Office of Chemical Hazards for Metals, said that the agency did
not set separate PELs for welding or other infeasible sectors because
these operations may occur at sites with other work activities, and
separate PELs would make enforcement of the standard
difficult.
Feasible Costs at Final Limit.
Overall, OSHA said, the estimated total annualized compliance costs
for the final PEL is more than $282 million, compared with more than
$570 million for the proposed PEL.
The total first-year compliance costs for the new requirements of
the final standard, OSHA added, are estimated to be more than $601
million.
However, the agency added, for the most part the rule is
economically feasible because none of the affected industries, for
which OSHA found that the costs of complying with the standard will be
less than both 1 percent of prior revenue and 10 percent of prior
profits, will be threatened by the standard.
OSHA was concerned about electroplating job shops at a lower PEL,
the agency added, since at 1 microgram per cubic meter the rule's cost would
represent 2.7 percent of revenues and 65 percent of profits.
At a PEL of 5 micrograms per cubic meter, the job shops have costs as a
percentage of profits of 30 percent and costs as a percentage of
revenues of 1.24 percent, OSHA said.
Notable Requirements.
Other provisions of the final rules include:
• an
exemption for work operations that can demonstrate that under no
expected conditions will concentrations of hexavalent chromium be
above 0.5 microgram per cubic meter;
• a
choice between performance-based monitoring or a more traditional
scheduled exposure determination option; and
• an
exposure-based trigger for employee medical surveillance at 30 or more
days of exposure above the action level, which is one-half the
PEL.
The final rule also extends the Portland cement exclusion in the
construction rule to also include shipyards and general industry. The
low CrVI content of Portland cement effectively limits inhalation
exposures under the current PEL for cement, OSHA
said.
Staggered Effective Dates.
Provisions of the final rule will be effective on staggered dates,
OSHA said.
The final standards will be effective on May 30, Snare said, but
the "start-up date" for the rule's provisions--except
engineering controls--will be Nov. 27. For employers with fewer than
20 employees, the start-up date will be May 30, 2007, he added.
The engineering control provisions, Snare continued, will not be
effective until May 31, 2010.
In deciding to allow employers four years, rather than two years,
to comply with the engineering control provisions of the standard,
OSHA noted that the expanded dates will reduce the one-time initial
costs of the standard by spreading them out over time.
By Lauren Couillard
For more information on the final CrVI rule, contact Kevin Ropp,
Office of Communications, at (202) 693-1999. The text of the rule is
reproduced in the Textsection of this
issue. Text of the rule and preamble is available at
http://es.bna.com/federal1/20060228/dol71p10100rule20060228.html
on the Web.